The 118 metre new bridge over Mochu River under Chhuboog Gewog in
Punakha is now open. The bridge at Bali village, will benefit some 27
households under Chhuboog Gewog. The new bridge will benefit especially
the students and villagers of Bali.
In the absence of a bridge, students have to cross Mochu River, which is the only short route until the bridge was opened. The other route to the school is a two hour walk from the village.
In the absence of a bridge, students have to cross Mochu River, which is the only short route until the bridge was opened. The other route to the school is a two hour walk from the village.
The bridge was constructed 11 months, at a cost of Nu 1.2 million with funds from Helvetas, and labour contribution from the beneficiaries.